Client: Hyperscale Data Centre Developers
Services: Power System Modelling & Analysis – Load Flow and Short Circuit Analysis to IEC 60909 | Transformer Thermal Assessment to IEC 60076 | MV / LV protection coordination
Location: Norway
Date: February 2026
Network Configuration: MV Ring with 32 IT Transformers and 8 mechanical transformers

Effective data centre design should be proven before energisation. Fault levels must remain within switchgear ratings. Electrical protection systems must discriminate across MV and LV. Transformers must stay within thermal limits in both normal operation and emergency power conditions. These outcomes cannot be assumed. They must be demonstrated through structured modelling and study outputs that stand up to technical review.
Engineering Power Solutions supported a new 36 MW data centre development in Scandinavia with specialist power system studies. The objective was to validate the electrical network across all normal, emergency and network configuration scenarios and confirm compliance with the relevant IEC standards prior to installation and commissioning.
Why Modelling Matters in Hyperscale Electrical Design
Large-scale facilities typically combine MV rings, RMUs, UPS-backed and utility-backed systems, and redundancy strategies that determine how the network behaves under stress. The most demanding scenario is often not the normal operating condition. During emergency power scenarios, particularly when UPS recharge coincides with peak demand, loading increases and fault contribution can shift materially.
Without a verified model, projects can carry avoidable risk into late design and commissioning, including equipment fault rating capacities (fault duty exceedance), loss of discrimination, thermal overloads in contingency operations, and redesign once equipment has already been procured.

Project Scope and Technical Framework
The facility incorporated 32 IT transformers and eight mechanical transformers arranged within an MV ring configuration. EPS developed a complete network model within ETAP and assessed the following criteria:
- Maximum and minimum demand scenarios across various normal and emergency network conditions
- Three-phase and single-phase-to-earth fault levels in accordance with IEC 60909
- Transformer thermal loading assessment against IEC 60076
- Protection coordination across the MV and LV network
EPS also studied the most onerous condition identified by the project team: A complete failure of half the electrical distribution network with the UPS recharging, resulting in a network demand of approximately 36.2 MW.

Short Circuit Analysis Identified a Critical Constraint
The short circuit assessment highlighted a material issue. With both transformers operating in parallel, the calculated fault level (fault duty) exceeded 100% of the RMU switchgear rating. On that basis, parallel transformer operation could not be permitted within the intended operating philosophy, and the project team used this finding to revise how the network would be operated and controlled.
Catching this constraint early in the design process avoided the risk of discovering it at commissioning or operation phase, when mitigations can become disruptive and expensive. Depending on the stage of delivery, the alternatives could have included uprating the RMUs or enforcing operational restrictions.
All remaining fault scenarios assessed across IT, mechanical and UPS-backed systems remained within equipment ratings.
Load Flow Performance Under Peak Demand
Load flow analysis confirmed stable network behaviour across all possible operating scenarios, aside from the identified transformer constraint. During the 36.2 MW failover and recharge scenario:
- Transformer utilisation peaked at 62%
- MV and LV voltages remained within the project voltage criteria (+6% / −10%)
- Cable loading stayed within thermal limits
- Voltage drop across the network remained minimal
This provided evidence that the selected transformer’s tap settings and equipment ratings delivered appropriate operating margin under worst-case demand.
Protection Coordination Strategy
EPS developed a three-stage overcurrent protection scheme on transformer feeders to ensure discrimination between upstream and downstream devices while remaining within transformer thermal damage limits. Protection grading across the IT infrastructure and auxiliary mechanical system infrastructure (HVAC, Cooling, etc.) was validated under both utility and UPS operation. This reduced the risk of nuisance tripping while maintaining alignment with recognised coordination principles and the upstream feeder philosophy.

Engineering and Commercial Impact
The study programme provided a defensible engineering basis for design decisions before energisation. Rather than reacting during commissioning, the project team could act on quantified evidence at the design stage.
In practical terms, we:
- Identified a non-compliant transformer operating configuration early enough to revise the operating philosophy
- Confirmed switchgear, transformer and cable adequacy under worst-case loading and failover scenarios
- Reduced the risk of late-stage redesign, equipment uprating and programme delay
- Provided IEC-aligned technical justification to support technical review and stakeholder approval
- Enabled a more predictable and controlled commissioning process
By resolving constraints before energisation, the client avoided avoidable capital adjustment and operational uncertainty.
Outcome
Subject to resolution of the transformer operating constraint through agreed operational controls and design measures, the network was confirmed as fault-level compliant, thermally adequate, protection coordinated, and suitable for the intended operating modes. EPS provided the technical evidence required to support commissioning and long-term operational stability.